Camera track system installation 02/02/2015 - Installation of camera track system begins in East bay. First section in position for assembly after approximately 3 hours. 02/03/2015 - Installation continues 02/09/2015 - Track in place and all sections connected along side LEO East.
Irrigation maintenance 02/03/2015 - East bay irrigation valve manifold removed by Tim to perform complete rebuild (07:30). 02/06/2015 - Rebuild of East bay irrigation valve manifold completed. Three of the electric actuators moved to West and Center hill slopes to replace faulty actuators. East bay will be missing three electric actuators until repair or replacement.
Camera track system installation
02/02/2015 - Installation of camera track system begins in East bay. First section in position for assembly after approximately 3 hours.
02/03/2015 - Installation continues
02/09/2015 - Track in place and all sections connected along side LEO East.
Irrigation maintenance
02/03/2015 - East bay irrigation valve manifold removed by Tim to perform complete rebuild (07:30).
02/06/2015 - Rebuild of East bay irrigation valve manifold completed. Three of the electric actuators moved to West and Center hill slopes to replace faulty actuators. East bay will be missing three electric actuators until repair or replacement.