CSAT3 redeployment

As we continue to spin up gas flux measurements, CSAT3s will be installed as needed.

Currently, CSAT3 S/N 2678 has been reinstalled in the LEO east bay as of 12/12/2023.

EX81 flow meters zero reset

All three ex81 zeros were reset. This was done between 1-2pm.

We have been seeing non-zero flow rates when there is no flow.

Currently, Center bay seems to be metering less flow with quick initial test with MP2000.

Further evaluation will be done.